Capabilities
We are experienced and capable of all types of utilities, water treatment, waste
water and water monitoring and controls projects. Review our projects list
for detail experience.
Project Experience
MCAS Water Supply Pump Station Modernization
Marie Corp. Air Station, Yuma,
Arizona - System Integrator
MCAS
modernized the water treatment plant by adding new VSD pumps and PLC based
control system to maintain base water supply. Responsibility
included project management of the control system, new PLC control
panel and termination panel, design submittals, manuals training, startup,
materials
design, configuration, debugging and integration of
Man-Machine interfaces to /PLC-based control system,
for controlling all aspects of the wastewater
treatment facility. Graphic screens were developed
in Intouch Wonderware. Ending
the project at 500 total Wonderware tag count. The project was set up to
work through a stand-alone-workstation. PLC
programming was done with Modicon TSX Quantum with
an Ethernet and Modbus Plus interface.
Kitsap Pump Station
Kitsap County, Kitsap,
Washington - System Integrator
Kitsap installed a new pump
station to expand there ability to control their waste water management. The
project
scope demanded the responsibility for controls and
instrumentation for a new 5000 GPM three pump, pump
station. The pumps had a vertical shaft and
were variable seed drives, with multiple pumping sequences for lead, lag,
and backup. Such safety requirements as a backup
generator, hazardous gas monitoring, chemical additives and radio alarm
system were also needed. 12
graphic screens for an Allen
Bradley Panel view display terminal were developed
using Panel builder 32 in conjunction with
RSLogic for the AB PLC5/03, PLC programming.
AutoCAD was also coordinated to develop multiple
drawings for designing control panel and instrumentation. Submittals,
testing, training, performance review, startup and documentation
were all part of making this project clean and well done.
Gresham Waste Water
Improvements
City of Gresham, Gresham, Oregon
The city of Gresham project required the integration
of an existing Wonderware application into a new Wonderware application that
doubled the size of the facility. Thirty new graphic screens were added and 25
existing screens were integrated into one application. All integration was done
online, maintaining operation of facility while adding new networks, PLCs and control systems.
Longview Water
Treatment SCADA
City of Longview, Longview,
Washington - System Integrator
Developed 40 graphic screens on a
single Wonderware control station connected to a TI-505 PLC to control the
operation of city water supply. Project also included alarm logging,
automatic report generation, field checkout, computer setup, startup,
training and project management.
Camas
Waste Water Treatment Improvements
City of Camas, Camas,
Washington - System Integrator
In the city of
Camas project we were responsible for the
design, configuration, debugging and integration of
Man-Machine interfaces to /PLC-based control system,
for controlling all aspects of the wastewater
treatment facility. Graphic screens were developed
in Intouch Wonderware. Ending
the project at 1500 total Wonderware tag count. The project was set up to
work through 5 distributed stations. PLC
programming was done with 5 Modicon TSX Quantum
PLCs. A network had to be
designed to accommodate the five stations, using a
five hub Ethernet and Modbus connection the
network worked without flaw. To wrap up the project we did a field
checkout and gave some startup training.
Bandon
Water Treatment Improvements
City of Bandon, Bandon,
Oregon - System
Integrator
Here we were also responsible for
the design, configuration, debugging and integration
of Man-Machine interfaces to /PLC-based control
system, for controlling all aspects of
the wastewater treatment facility.
Graphic screens were also developed
in Intouch Wonderware. Ending
the project at 800 total Wonderware tag count.
Silverton Wastewater Treatment Improvements
City of Silverton,
Silverton, Oregon -
System
Integrator
As well
here we were responsible for
the design, configuration, debugging and integration
of Man-Machine interfaces to /PLC-based control
system, for controlling all aspects of
the wastewater treatment facility.
Graphic screens were also developed
in Intouch Wonderware. Ending
the project at 1200 total Wonderware tag count.PLC programming
was done with an Allen-Bradley SLC504
PLC. To wrap up the project we did a field
checkout and gave some startup training.